to another by lifting them 
bodily by jacks, and putting in filler pieces before releasing the jacks, 
not trusting to wedging to transfer the loads. In fact, apart from the 
boxing-in of the surface railway concrete, no wedges whatever were 
used. This appears to have been a decided advantage, for, with the 
constant pounding of trains on the elevated railway and the jarring due 
to heavy trucks on the pavement blocks, it is very likely that wedging 
would have become loosened and displaced, whereas, with blocking, 
there was little or no tendency toward displacement due to vibration. 
Although the vibration of the structure, when a long length was 
supported on girders "C" resting on the permanent viaduct girders on 
the sides of the avenue, appeared to be considerable, not only vertically 
but transversely, very careful observation showed that the sag in the 
girder "C" due a live load of three elevated railway trains, one surface 
railway car, and one heavy truck, amounted to 1/8 in. The sideway 
vibration did not amount to more than 1/32 in. on either side of the 
normal position. More vibration was caused by heavy trucks and 
wagons going over the stone pavement than by the elevated railway 
trains or surface cars. 
No blasting was done near the supports of the elevated railway 
structure while trains were passing over it, and occasionally trains were 
stopped during a heavy or uncertain blast. A watchman on the surface, 
day and night, and at first one and later two flagmen on the elevated 
railway structure, were on duty at all times, reporting to the 
Interborough Rapid Transit Company, by whom they were employed. 
Log mats and timber protection for the girders and the columns of the 
permanent viaduct were used, as shown by Figs. 1 and 4, Plate XLIX, 
during the excavation of the rock core, and timber was also used to 
protect the face of the completed portions of the concrete abutments. 
In excavating the sides of the avenue, the rock broke better on the east 
than on the west side, where large seams developed and some slides 
occurred. 
_Abutments._--As shown on Fig. 7, the face of the north abutment has
a batter of 2 in. to the foot, and the face of the south abutment has a 
variable batter, the base being on a grade and the bridge seat being 
level, and both maintaining a uniform distance from the center of the 
Terminal Yard. The back walls of the abutments were not built until the 
steel had been put in place. 
No attempt was made to water-proof these abutments, but, in the rear of 
the wall, open spaces were left, about 6 ft. from center to center, which 
were connected with drain pipes at the base of and extending through 
the wall, for the purpose of carrying off any water that might develop in 
the rock. These drains were formed by building wooden boxes with the 
side toward the rock open and the joints in the boxes and against the 
rock plastered with mortar in advance of the wall. A hose was used to 
run water through these drains during the placing of the concrete, for 
the purpose of washing out any grout which might run into them. Each 
box was washed out at frequent intervals, and there was no clogging of 
the drains whatever. This method of keeping the drains open was 
adopted and used successfully for the entire work. The abutments were 
built of concrete, and the mixture was 1 part of cement, 3 parts of sand, 
and 6 parts of broken stone. 
The concrete was mixed in a No. 3 Ransome mixer, and was placed 
very wet. No facing mixture or facing diaphragms were used, but the 
stone was spaded away from the face of the wall as the concrete was 
laid. Chutes were used inside the form, if the concrete had to drop some 
distance. Work was continued day and night, without any intermission, 
from the time of commencement to the time of completion of each 
section. 
The face of the concrete wall was rubbed and finished in a manner 
similar to that used on the walls between Ninth and Tenth Avenues, as 
described later. 
Fig. 2, Plate LII, shows the east and central portions of the south 
abutment, completed and carrying the permanent viaduct, and the 
excavation completed for the west portion. 
WORK BETWEEN NINTH AND TENTH AVENUES.
_General Description._--The work involved the excavation of about 5.4 
acres, between the west house line of Ninth Avenue and the east house 
line of Tenth Avenue, to an average depth of about 50 ft., the 
construction of a stone masonry portal at Tenth Avenue leading to the 
River Tunnels, and the construction around the site of the concrete 
retaining and face walls. 
The following estimated quantities    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.