Avenue a 
cut which came to the grade of 32d Street about midway between Ninth 
and Tenth Avenues, and a trestle was constructed from this point over 
Tenth Avenue and thence to the disposal pier at the foot of West 32d 
Street. 
On May 11th, 1906, the work of excavation was commenced on the 
east side of Ninth Avenue, and on July 9th, 1906, on the south side of 
31st Street, between Ninth and Tenth Avenues. From the beginning, the 
excavation was carried on by day and night shifts, except on Sundays 
and holidays, until January, 1909, except that during the period from 
November, 1907, to October, 1908, the night shift was discontinued. 
_Geology._--The rock encountered may be classed as "gneiss"; its 
character varied from granite to mica schist. It was made up of quartz, 
feldspar, and mica, and there were also some isolated specimens of 
pyrites, hornblend, tourmaline, and serpentine. On the south side of the 
work, just west of Ninth Avenue, there were excellent examples of 
"contortions" of veins of quartz in the darker rock. On the east side of 
Ninth Avenue, near the north end of the work, glacial marks were 
found on the rock surface. The general direction of the stratification 
was north 5° west, and the general incline about 60° with the horizontal. 
As a rule, the rock broke sharply along the line of stratification. On the 
south side it broke better than on the north side, where it was usually 
softer and more likely to slide; and this, together with the fact that in 
winter it was subject to alternate freezing and thawing and in summer 
to the direct rays of the sun, made it rather difficult to get a good 
foundation for the retaining walls. 
WORK IN AND UNDER NINTH AVENUE. 
_General Description._--The work involved the excavation of about
375 ft. of the full width of Ninth Avenue to an average depth of about 
58 ft., and the construction over this area of a steel viaduct, the deck of 
which was about 24 ft. below the surface, for the ultimate support of 
the Ninth Avenue structures. 
The following estimated quantities appear in the contract: Excavation 
of rock, 72,600 cu. yd.; excavation of all materials except rock, 9,300 
cu. yd.; concrete (1:3:6) in abutments, etc., 1,680 cu. yd.; timber, 
504,000 ft., B.M.; structural steel, 1,320,000 lb., etc. 
While this excavation was being done it was necessary to support and 
maintain the three-track elevated railway structure of the Interborough 
Rapid Transit Company, of which 18 columns, or a length of about 340 
ft., were affected, the two-track surface railway structure of the New 
York City Railway Company, and various pipes, sewers, and conduits, 
and to maintain all surface vehicular and pedestrian traffic. All 
structures were left in place with the exception of the pipes, most of 
which were temporarily cut out. The 48-in. brick sewer in the center of 
Ninth Avenue was broken, and the sewage was pumped across the 
excavation through a smaller pipe. 
The general method adopted was as follows: The east and west sides of 
the avenue were closed, vehicular traffic was turned into the center, and 
a trestle for pedestrians was constructed west of the westerly elevated 
railway columns. All structures were then supported on transverse 
girders, running across the avenue, below the surface, and these rested 
on concrete piers on the central rock core. The sides of the avenue were 
then excavated to sub-grade, and the permanent steel viaduct was 
erected on both sides of the avenue as close as possible to the central 
rock core. The weight of all structures was then transferred to the 
permanent steel viaduct, erected on the sides of the avenue, by timber 
bents under the transverse girders resting on the permanent steel 
viaduct, and all weight was thus taken off the central rock core. This 
core was then excavated to sub-grade, the permanent viaduct was 
completed, and all structures were placed on its deck, using concrete 
piers and timber bents. 
The design and erection of the permanent steel viaduct and the
permanent foundations on its deck were done under another contract, 
apart from the North River Division work, and are not described in this 
paper. 
_Elevated Railway Structure of the Interborough Rapid Transit 
Company._--The Ninth Avenue Elevated Railway was built between 
1877 and 1880 as a two-track structure, the design being such as to 
permit a third or central track to be added later, and this was built in 
1894. It is supported on columns under the outside tracks, about 43 ft. 
from center to center longitudinally and 22 ft. 3 in. from center to 
center transversely, the central track being carried by transverse girders 
between the columns. 
The columns carrying the structure are of fan top design, with the 
points of bearing near the extremities    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
 
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.
	    
	    
