appear in the contract: Excavation 
of rock in trenches, 3,400 cu. yd.; excavation of rock in pit, 377,000 cu. 
yd.; excavation of all materials except rock in trenches, 6,500 cu. yd.; 
excavation of all materials except rock in pit, 34,000 cu. yd.; concrete, 
1:3:6, in retaining walls, 4,580 cu. yd.; concrete, 1:3:6, in face walls, 
7,460 cu. yd.; concrete, 1:2:3, with 3/4-in. stone, in face walls, 4,100 cu. 
yd.; stone masonry in portal, 247 cu. yd., etc., etc. 
[Illustration: Fig. 7. (Full page image) 
NINTH AVE. ABUTMENTS & KEY PLAN] 
As previously stated, the contract price included the placing of all 
excavated material on scows at Pier 62, North River. Prior to this 
contract this pier had been used by the New York Contracting 
Company-Pennsylvania Terminal, for the disposal of excavated 
material from east of Ninth Avenue. In order to get the material to the 
pier, the contractor had excavated a cut under Ninth Avenue which 
came to the grade of 32d Street about midway between Ninth and 
Tenth Avenues, and a trestle was constructed from this point over 
Tenth Avenue and thence to the pier. Fig. 2, Plate XLVII, shows the 
east end of this cut, and Fig. 1, Plate L, shows the trestle, looking east 
from Tenth Avenue. 
A 30-ton steam shovel was brought to the south side of the work, and 
commenced operating on July 9th, 1906. After working there about a 
month, the earth had been practically stripped off the rock, and the 
shovel was moved over to the north side where it excavated both earth 
and rock until August 10th, 1907. 
At three points south of 32d Street and at one point north of 32d Street
near Tenth Avenue, cuts were made in the rock to sub-grade, and from 
these cuts, together with the cuts on the west side of Ninth Avenue, all 
widening out was done and the excavation was completed. Fig. 1, Plate 
L, shows the excavation of the three cuts on the south side of 32d Street, 
the steam shovel operating on the north side of that street, and the 
material-disposal tracks and trestle. Fig. 3, Plate LII, shows the cuts 
joined up and the excavation along the south side practically 
completed. 
On the north side of the work, between Stations 182 + 90 and 183 + 65, 
the rock was low, and provision had to be made for maintaining the 
yards to the north of the site. Therefore a rubble-masonry retaining wall 
was built, with the face about 2 ft. north of the face of the proposed 
concrete wall which was to be put in later. On the same side of the 
work, between Stations 188 + 24 and 188 + 46, the rock was 
exceedingly poor, and as a small frame house on the adjoining lot was 
considered to be in an unsafe condition, a rubble masonry retaining 
wall was built. As the building adjoining the south side of the work at 
Tenth Avenue was on an earth foundation, it was necessary to underpin 
it before the excavation could be done. The building was supported on 
needles, and rubble masonry was put in from the bottom of the old 
foundation to the rock. The foundation of 413 West 31st Street, 
immediately west of the Express Building site, was of very poor 
masonry, and it was necessary to rebuild it prior to taking out the 
adjoining excavation. 
[Illustration: PLATE L, FIG. 1.--TW 23, P.N.Y. & L.I.R.R. Terminal 
Station West. View looking Eastward from Tenth Ave., showing work 
between Ninth & Tenth Avenues. Dec. 26, 06.] 
[Illustration: PLATE L, FIG. 2.--TW 35, P.T. & T.R.R. Co. Terminal 
Station West. View looking Northwest from Sta. 184, 120 feet South of 
center line. Dec. 31, 07.] 
[Illustration: PLATE L, FIG. 3.--TW 96, P.T. & T.R.R. Co. N.R. Div. 
Terminal Station West. View looking West from Ninth Avenue 
Elevated Railway, showing condition of work. May 26, 09.]
[Illustration: PLATE L, FIG. 4.--TW 104, P.N.Y. & L.I.R.R. Terminal 
Station West. View from Tenth Avenue looking East, showing progress 
of concrete walls. Aug. 7, 09.] 
Along the north side, between Stations 186 + 50 and 187 + 50, the 
walls supporting the adjoining back yards were of poor quality and had 
to be renewed by the contractor before excavation could be done. 
The excavated material was loaded by derricks on cars at the top of the 
excavation, these cars being on tracks having a direct connection with 
the disposal trestle, as shown by Fig. 1, Plate L. As soon as it could be 
done, derricks were placed at the bottom of the excavation; tracks were 
then laid out there, and the excavated material was loaded on cars at the 
bottom and hoisted by derricks to cars on the disposal trestle. A 
locomotive was lowered to the bottom of the    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.