sewage carried through Pipe R. Foot 
Walk carried on Girders C in place on West Side of Avenue. 
No. 4 
Elevated Railway carried on Bents under Columns. Temporary Shoring 
Girders removed and Permanent Bents resting on Girders C in place. 
Bents in place on Girders C carrying Surface Railway. East and West 
sides of Avenue excavated down to Sub-Grade and Five rows of 
Permanent Steel in place on each side. Bents erected on Permanent 
Steel to catch ends of Girders C while 2 outside Concrete Piers are 
removed and 6th row of Permanent Steel on each side is put in place. 
No. 5 
Two outside Concrete Piers removed and 6th row of Permanent Steel in 
place. Girders C carrying all structures now resting on Bents on 
Permanent Steel. 48" C.l. Sewer carried on Brackets on Girders C. 
No. 6
Excavation Completed. ] 
Temporary raker braces were placed against the structure to prevent 
lateral movement. Four sets of these temporary shoring girders were 
used in this manner, two sets starting at the north end and two sets at 
about the middle of the work, and these sets were moved south as they 
were released. 
The columns being thus supported on temporary shoring girders, the 
old foundations were removed and the excavation was taken down to a 
level about 16 ft. below the surface. 
Two sets of three of the girders "C" were then put in place under the 
avenue at each column, each set being placed on four concrete piers 6 ft. 
square with spaces of 4 ft. between them, so that the outside of the 
outside pier would be 18 ft. from the center of the avenue and 32 ft. 
from the house line. This is shown on Fig. 5 and on Fig. 3, Plate XLVII. 
Four small piers were used, as they could be more easily removed than 
one continuous pier. The girders "C" were set to line and grade, and the 
piers were built under them, great care being taken to get the concrete 
well under the girders so as to give a firm bearing. 
After these girders "C" were in place it was necessary to remove the 
temporary shoring girders before the bents could be erected on girders 
"C" to support girders "B," being in the same plane; and provision had 
to be made to support the structure while this was being done. 
Therefore, double bents were erected directly beneath the columns, as 
shown by Figs. 2, 4, and 5, and by Fig. 3, Plate XLVII. These were 
built with their sills resting on the girders "C," and blocking was put in 
between the sills and the rock to carry the full weight of the structure. 
Later, when the weight of the structure was carried on the permanent 
bents, this blocking was knocked out, but the bents were left in to carry 
the weight of the column itself, which was swinging more or less from 
the structure above. The weight of the structure was placed on these 
bents directly beneath the columns by jacking up the temporary girders 
again, putting blocking between the bents and the base of the columns, 
and taking out the blocking which had been put in previously under the 
temporary shoring girders. The 24-in. water main was carried over the
excavation on cables from the temporary shoring girders, except when 
they were being jacked up, at which time posts were placed beneath it. 
Anchor-bolts were put in place between the column bases and the bents 
directly beneath, in order to increase the lateral stiffness, and raker 
braces were also used. This having been done, the temporary shoring 
girders were moved south to the next column, where the process was 
repeated. The timber bents, shown in detail by Fig. 2, were then put in 
place as shown by Figs. 4 and 5, and by Fig. 3, Plate XLVII. These 
bents were framed as tightly as possible, using generally a 20-ton jack, 
and they were erected simultaneously at each pair of columns. The 
weight was taken on these columns by jacking up directly beneath the 
column base and taking out the blocking between this base and the bent 
directly beneath the column. On releasing the jack the weight was 
transferred to the permanent timber bents, and the east and west 
columns of each pair were transferred on the same day. One 80-ton jack 
was used on the easterly columns and two were necessary on the 
westerly columns, one on each side of the 24-in. water main. The raker 
braces of these permanent bents were not framed as tightly as the main 
posts, in order that the main post should carry the entire weight and the 
raker braces merely steady the structure. 
Timber bents were erected on girders "C" to carry the I-beams under 
the surface railway structure,    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.