were 
mined out, and the structure was supported on I-beams and posts, and 
ultimately on the transverse girders by using timber bents under the 
I-beams, as shown on Fig. 3. 
_Water Mains and Sewer._--Cradles were designed for the support of 
the 48-in. and 24-in. water mains, resting on the transverse girders, and
the 48-in. cast-iron sewer on the east side of the avenue was carried on 
I-beams bracketed to the ends of the transverse girders, as shown on 
Figs. 1 and 2. 
[Illustration: FIG. 2. (Full page image) 
METHOD OF SUPPORTING ELEVATED RAILWAY 
STRUCTURE] 
[Illustration: FIG. 3. (Full page image) 
METHOD OF SUPPORTING TRACKS OF NEW YORK CITY 
RAILWAY CO.] 
_Girders "C."_--The transverse girders below the street surface, 
referred to above, were known as girders "C," and they were put in 
place at first resting on concrete piers on the central core; the weight of 
all structures was placed on them while the sides of the avenue were 
being excavated, and the sides of the viaduct were being built. The ends 
of these girders were then picked up on the sides of the viaduct, and, 
spanning the central rock core, carried all structures while the core was 
being excavated and the viaduct completed. New foundations were then 
placed on the deck of the viaduct to carry all structures. 
Fifty-four of these girders were required, each weighing about 19,000 
lb. The bents carrying the ends of these girders on the sides of the 
viaduct are shown on Fig. 2. They were of long-leaf yellow pine. These 
girders were located so that a cradle could be laid on them east of the 
elevated railway structure to carry a proposed 48-in. cast-iron water 
main. 
_Girders "B."_--Eighteen of these girders were required, each weighing 
about 6,000 lb. The timber bents supporting these girders, shown on 
Fig. 2, were of long-leaf yellow pine. 
The total weight, including the elevated railway structure, surface 
railway structure, pipes, etc., supported during the work, amounted to 
about 5,000 tons.
_Details of the Work._--The method in general is shown on Figs. 4 and 
5. At first the east side of the avenue was closed and excavated down to 
rock, the earth was mined out under alternate yokes of the surface 
railway structure, and temporary posts were placed under the yokes to 
support the structure while the remainder of the earth was being 
removed. Then needle-beams and posts were placed under each yoke. 
The concrete forming the track structure was then enclosed with 
planking to prevent it from cracking and falling. I-beams were then 
placed under the needle-beams carrying the structures, and these were 
carried on posts; they were changed alternately until the excavation had 
been taken out to a depth of about 16 ft. below the surface. In placing 
these I-beams, heavier blocking was used in the center of the span than 
at the ends where the bents would come, to prevent the subsidence of 
the track owing to the sag in the I-beams. As much excavation, to a 
depth of about 20 ft., was taken out adjoining the elevated railway 
foundations as could be done with safety. Fig. 2, Plate XLVII, shows 
this condition of the work. The 48-in. brick sewer was broken, and the 
sewage was pumped across the excavation. 
The overhead girders "B" were then put in place, and two of the girders 
"C" were used as temporary shoring girders at each column. These, as 
shown by Fig. 3, Plate XLVII, were placed parallel to the elevated 
railway, with blocking between them and the girders "B." Double bents, 
independent of each other, were placed under the ends of these 
temporary shoring girders, and these were braced securely to prevent 
possible dislodgment during the removal of the rock. The weight of the 
structure was then taken by jacking up the girders near the bents until 
the column was lifted off the old foundation; blocking was put in 
between the girders and the bents during the jacking, so that when the 
jacks were released the base of the column was still clear of the old 
foundation. One 80-ton jack was used for this purpose, and the general 
method is shown by Fig. 1, Plate LII. 
[Illustration: FIG. 4. (Full page image) 
METHOD OF EXCAVATING NINTH AVENUE PLAN AND 
ELEVATION SHOWING VARIOUS STAGES OF THE WORK]
[Illustration: FIG. 5. (Full page image) 
METHOD OF EXCAVATING NINTH AVENUE SECTIONS 
SHOWING VARIOUS STAGES OF WORK 
No. 1 
Condition Prior to Commencement of Work 
No. 2 
East side of Avenue cut down about 20 ft. Beams with Supporting 
Posts placed under Surface Railway Tracks. Girders B and Temporary 
Shoring Girders C for supporting Elevated Ry. in place. 
No. 3 
I's in place under Surface Ry. Tracks. Elevated Ry. carried on 
Temporary Shoring Girders, and Girders C in place. 24" Water Main 
carried on Timber Cradle and    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.