Transactions of the American 
Society of
by James H. Brace 
and Francis Mason 
 
The Project Gutenberg EBook of Transactions of the American Society 
of 
Civil Engineers, Vol. LXVIII, Sept. 1910, by James H. Brace and 
Francis Mason This eBook is for the use of anyone anywhere at no cost 
and with almost no restrictions whatsoever. You may copy it, give it 
away or re-use it under the terms of the Project Gutenberg License 
included with this eBook or online at www.gutenberg.org 
Title: Transactions of the American Society of Civil Engineers, Vol. 
LXVIII, Sept. 1910 The New York Tunnel Extension of the 
Pennsylvania Railroad. The Cross-Town Tunnels. Paper No. 1158 
Author: James H. Brace and Francis Mason 
Release Date: August 13, 2006 [EBook #19037] 
Language: English 
Character set encoding: ISO-8859-1 
*** START OF THIS PROJECT GUTENBERG EBOOK 
TRANSACTIONS OF THE AMERICAN *** 
 
Produced by Juliet Sutherland, Jacqueline Jeremy and the Online
Distributed Proofreading Team at http://www.pgdp.net 
 
AMERICAN SOCIETY OF CIVIL ENGINEERS 
INSTITUTED 1852 
TRANSACTIONS 
Paper No. 1158 
THE NEW YORK TUNNEL EXTENSION OF THE 
PENNSYLVANIA RAILROAD. THE CROSS-TOWN TUNNELS.[A] 
BY JAMES H. BRACE AND FRANCIS MASON, MEMBERS, AM. 
SOC. C. E. 
 
In this paper, it is proposed to describe the construction of the tunnels 
extending eastward from the easterly extension of the Terminal Station 
to the permanent shafts east of First Avenue. 
They were located under 32d and 33d Streets from the station to 
Second Avenue, and thence, curving to the left, passed under private 
property and First Avenue to the shafts, as described in a preceding 
paper. Typical cross-sections of the tunnels are shown on Plate XII.[B] 
On May 29th, 1905, a contract was entered into with the United 
Engineering and Contracting Company for the performance of this 
work. This contract provided that work on each pair of tunnels should 
be carried on from two shafts. The first, here referred to as the First 
Avenue Shafts, were located just east of that avenue and directly over 
the line of the tunnels; the other two, called the Intermediate Shafts, 
were located on private property to the north of each pair of tunnels in 
the blocks between Fourth and Madison Avenues. It was originally 
intended to do all the work of construction from these four shafts. 
Workings were started both east and west from the Intermediate Shafts,
and those to the west were to be continued to the Terminal Station. 
After the change of plans, described in a previous paper, it was decided 
to sink a third shaft on each line. These were known as the West Shafts, 
and were located between Sixth and Seventh Avenues. Finally, it was 
found necessary to build a portion of the tunnels on each line west of 
Sixth Avenue in open cut. The locations of the shafts are shown on 
Plate XIV.[C] 
The First Avenue shafts were built by S. Pearson and Son, Inc., for the 
joint use of the two contractors, as described in the paper on the tunnels 
under the East River. While the shafts were being sunk, the full-sized 
tunnels were excavated westward by the contractor for the river tunnels 
for a distance of 50 ft., and top headings for 50 ft. farther. By this 
means, injury to the caissons and to the contractor's plant in the shafts 
by the subsequent work in the Cross-Town Tunnels was avoided. The 
west half of the shaft was for the exclusive use of the contractor for the 
Cross-Town Tunnels. 
CONTRACTOR'S PLANT. 
The method of handling the work adopted by the contractor was, 
broadly speaking, as follows: Excavation was usually carried on by 
modifications of the top-heading and bench method, the bench being 
carried as close to the face as possible in order to allow the muck from 
the heading to be blasted over the bench into the full section. The spoil 
was loaded into 3-yd. buckets (designed by the contractor and 
hereinafter described), by steam shovels operated by compressed air, 
and hauled to the shafts by electric locomotives. Electrically-operated 
telphers, suspended from a timber trestle, hoisted the buckets, and, 
traveling on a mono-rail track, deposited them on wagons for 
transportation to the dock. Arriving at the dock, the buckets were lifted 
by electrically-operated stiff-leg derricks and their contents deposited 
on scows for final disposal. The spoil was thus transported from the 
heading to the scow without breaking bulk. 
When concreting was in progress, the spoil buckets were returned to 
the shafts loaded with sand and stone. The concrete materials were 
deposited in storage bins placed in the shafts, from which they were fed
to the mixers located at the foot of the shaft about on a level with the 
crown of the tunnels. The concrete was transported to the forms in 
side-dump, steel, concrete cars, hauled by the electric locomotives. 
Electrical power was adopted largely on    
    
		
	
	
	Continue reading on your phone by scaning this QR Code
 
	 	
	
	
	    Tip: The current page has been bookmarked automatically. If you wish to continue reading later, just open the 
Dertz Homepage, and click on the 'continue reading' link at the bottom of the page.
	    
	    
